Plumbline — Leveling: Plumbing
Plumbline
Projects · Westview Apartments Phase II · Leveling: Plumbing

Leveling — Plumbing (3 bids)

P.E. M. Holland · Bid due Fri 5/30 · Award by Mon 6/2
Lowest of three
Outlier (>15% above lowest)
Item not bid
Line items
Northstar Plumbing
Austin, TX · 12 prior jobs
$284,300.00
Submitted 5/24 Add ack'd
Bluewater Mechanical
San Marcos, TX · 4 prior jobs
$294,825.00
Submitted 5/23 Add ack'd
Lone Star Plumbing Co.
Round Rock, TX · 1 prior job
$311,400.00
Submitted 5/22 Add #2 pending
Underground
001
Underground sanitary, building A
1 LS
$32,500.00 $32,500.00 $34,200.00 $34,200.00 $38,900.00 $38,900.00
002
Storm drainage tie-ins
4 EA
$3,800.00 $15,200.00 $3,425.00 $13,700.00 $3,950.00 $15,800.00
Rough-in
003
Domestic water rough-in, units 1A–6F
218 EA
$612.00 $133,416.00 $648.00 $141,264.00 $685.00 $149,330.00
004
Sanitary waste & vent rough-in
218 EA
$385.00 $83,930.00 $362.00 $78,916.00 $415.00 $90,470.00
Fixtures & finish
005
Fixture sets — kitchen & bath
218 EA
$485.00 $105,730.00 $462.00 $100,716.00 $498.00 $108,564.00
006
Water heater allowance
218 EA
Excluded per clarifications $1,820.00 $396,760.00 Excluded
007
Roof drains + leaders
14 EA
$890.00 $12,460.00 $1,040.00 $14,560.00 $1,250.00 $17,500.00
008
Test, balance, commission
1 LS
$8,200.00 $8,200.00 $7,400.00 $7,400.00 $10,200.00 $10,200.00
Exclusions / Clarifications
  • Excludes water heaters; allowance handled separately
  • Sales tax not included
  • Wages per Davis-Bacon
  • Water heater allowance included at $1,820/unit
  • Sales tax not included
  • Open-trench excavation by GC
  • Excludes water heaters and roof curbs
  • Acknowledgement of Addendum #2 still pending
  • Premium-time labor excluded
Base bid total $284,300.00 — base
$294,825.00 +$10,525 (+3.7%)
$311,400.00 +$27,100 (+9.5%)
Northstar Plumbing
Austin, TX · 12 prior jobs
$284,300.00
Lowest of three — base
Submitted 5/24 Add ack'd
Underground sanitary$32,500
Storm drainage tie-ins$15,200
Domestic water rough-in$133,416
Sanitary waste & vent$83,930
Fixture sets$105,730
Water heater allowanceexcluded
Roof drains + leaders$12,460
Test & commission$8,200
Exclusions / clarifications
  • Excludes water heaters; allowance handled separately
  • Sales tax not included; wages per Davis-Bacon
Bluewater Mechanical
San Marcos, TX · 4 prior jobs
$294,825.00
+$10,525 (+3.7%) vs. lowest
Submitted 5/23 Add ack'd
Underground sanitary$34,200
Storm drainage tie-ins$13,700
Domestic water rough-in$141,264
Sanitary waste & vent$78,916
Fixture sets$100,716
Water heater allowance$396,760
Roof drains + leaders$14,560
Test & commission$7,400
Exclusions / clarifications
  • Water heater allowance included at $1,820/unit
  • Open-trench excavation by GC; sales tax not included
Lone Star Plumbing Co.
Round Rock, TX · 1 prior job
$311,400.00
+$27,100 (+9.5%) vs. lowest
Submitted 5/22 Add #2 pending
Underground sanitary$38,900
Storm drainage tie-ins$15,800
Domestic water rough-in$149,330
Sanitary waste & vent$90,470
Fixture sets$108,564
Water heater allowanceexcluded
Roof drains + leaders$17,500
Test & commission$10,200
Exclusions / clarifications
  • Excludes water heaters and roof curbs
  • Acknowledgement of Addendum #2 still pending